he construction industry has long struggled with late payment and the effect it has on cashflow throughout the supply chain. The Government’s Commercial Payments Bill proposes significant changes intended to address that issue, including new rules governing payment under construction contracts and, most significantly, the eventual abolition of cash retentions.
The Commercial Payments Bill has completed its stages in the House of Lords and was introduced into the House of Commons on 21 October 2026. It has not yet been enacted and may therefore be amended as it progresses through Parliament.
If enacted substantially in its current form, the Bill will make important changes to the payment landscape under the Housing Grants, Construction and Regeneration Act 1996 (the Construction Act) and could require parties across the construction industry to reconsider established contractual and commercial practices.
What does the Bill seek to achieve?
The Bill forms part of the Government’s wider attempt to tackle late and lengthy payment practices. According to Government figures, late payment costs the UK economy an estimated £11 billion each year, with approximately 14,000 businesses closing annually as a result.
Although much of the Bill applies across commercial contracts generally, construction receives specific treatment because an extensive statutory payment regime already exists under the Construction Act.
For construction businesses, the most significant proposals are:
- amendments to the statutory payment regime for construction contracts;
- stricter requirements concerning pay less notices;
- mandatory statutory interest on late payments; and
- a phased prohibition on cash retentions.
These changes are potentially significant for everyone in the construction chain, from developers and employers through to main contractors, subcontractors and specialist suppliers.
Changes to payment under construction contracts
The Bill proposes amendments to Part II of the Construction Act rather than simply applying the general commercial payment rules wholesale to construction contracts.
One particularly important change concerns pay less notices.
Under the Bill as currently drafted, a payer’s pay less notice will be ineffective if it is issued less than seven days before the final date for payment.
This is likely to have significant practical consequences.
At present, contracts commonly provide their own period between the deadline for serving a pay less notice and the final date for payment, subject to the Construction Act and Scheme for Construction Contracts. The proposed legislation would effectively impose a statutory minimum seven-day period.
Those administering construction contracts will therefore need to review their payment calendars carefully. Employers and contractors who leave valuation or payment decisions until shortly before the final date for payment could find themselves unable to serve an effective pay less notice.
Given the well-established consequences of failing to serve a valid payment notice or pay less notice, that is unlikely to be a merely administrative concern. It may increase the prospect of so-called “smash and grab” adjudications where the notified sum becomes payable because the appropriate notice has not been served in time.
The Bill also proposes changes to how periods of time are calculated in order to align the Construction Act regime with the wider commercial payment legislation. Contract templates and payment schedules will therefore need to be reviewed once the final legislation and accompanying regulations are known.
Statutory interest will become harder to avoid
The Bill also proposes strengthening the statutory right to interest on late commercial payments.
The legislation would imply a right to interest at 8% above the Bank of England base rate and contractual provisions seeking to exclude or vary that statutory entitlement would be void. For construction debts, interest would run from the day after the final date for payment.
This could have a significant effect in an industry where bespoke amendments frequently contain contractual interest provisions which are less generous than the statutory rate.
The practical effect is likely to be that delayed payment becomes more expensive. Employers, contractors and subcontractors will need more effective systems for approving applications, issuing notices and authorising payment within the contractual timetable.
The end of construction retentions?
The most significant construction-specific reform is the proposed prohibition on the deduction and withholding of retention sums.
Retentions remain a familiar feature of UK construction contracts. They typically permit the payer to withhold a percentage from interim payments, with amounts released at particular contractual milestones such as practical completion and the expiry of the defects rectification period.
The Bill proposes to prohibit new contractual provisions which permit the deduction or withholding of a retention sum under a construction contract or related agreement. It would also prevent the variation of existing contracts to introduce such provisions.
Importantly, abolition will not happen immediately.
The present Bill envisages a two-year transitional period leading up to the prohibition. Transitional retention sums would then be subject to statutory requirements governing their release, with a “last retention day” one year after the prohibition comes into force.
The Bill also proposes a powerful sanction where the employer does not pay a retention sum after the transition period ends, but the retention has become due: in this case the Bill implies a contractual term that would entitle the supplier to a fixed sum equal to the greater of £40 or 50% of the retention debt.
The detailed implementation timetable remains important. The Government has indicated that most of the reforms will be brought into force through commencement regulations following Royal Assent and that a package of secondary legislation will follow.
If there are no retentions, what replaces them?
Perhaps the more difficult question for the industry is not whether retentions should disappear, but what takes their place.
Retentions serve two broad purposes. They provide an incentive for contractors and subcontractors to return and rectify defects and provide employers and contractors with at least some financial security if they do not.
Once cash retentions disappear, parties may increasingly look to alternatives such as:
- retention bonds;
- performance bonds;
- parent company guarantees;
- escrow or project bank account arrangements;
- more extensive rights of set-off where legally permissible;
- enhanced defects and rectification provisions; and
- more rigorous practical completion processes.
Those alternatives are not necessarily equivalent to holding cash.
A bond, for example, introduces the cost of obtaining security and requires consideration of its wording, duration and the circumstances in which it can be called. Parent company guarantees will not be available where a contractor does not have a sufficiently substantial parent company and may provide limited protection where financial difficulties affect the wider corporate group.
There is therefore likely to be considerable focus on how defects security is structured once the prohibition comes into force.
A potential shift in risk at practical completion
The abolition of retention may also subtly change the commercial importance of practical completion.
Where retention is currently released in stages, the contractor continues to have a direct financial incentive to deal with outstanding defects and fulfil contractual obligations after practical completion.
If that incentive disappears, employers may become more cautious about certifying practical completion where there are outstanding items.
That could, in turn, make provisions dealing with practical completion, snagging and defects more contentious.
Contract drafting may therefore evolve to provide alternative mechanisms for dealing with incomplete or defective work without recreating something that amounts, in substance, to a prohibited retention arrangement.
Parties will need to take particular care here. The Bill is concerned not merely with contractual provisions labelled “retention”, but with provisions which in substance permit retention sums to be deducted or withheld.
The wider impact on the construction industry
For subcontractors, particularly SMEs, the reforms should offer a significant cashflow benefit. Money which historically might have remained tied up for months, and sometimes considerably longer, will instead become available to those businesses.
The reforms could also reduce the exposure of subcontractors to the insolvency of businesses higher up the contractual chain while retention sums remain outstanding.
That policy objective reflects a wider problem extending beyond construction. Government research estimates that around £26 billion is tied up in late payments at any given time, affecting some 1.5 million businesses annually.
For employers and main contractors, however, the picture is more complicated.
Removing retention does not eliminate the underlying risk of defective or incomplete performance. It changes the way that risk must be managed. Some of the cashflow benefit delivered to the supply chain may therefore be accompanied by increased demand for bonds and other forms of security, with the cost potentially finding its way back into tender prices.
Much will depend on how the market responds.
Will there be another adjudication regime?
The Bill would also considerably strengthen the role of the Small Business Commissioner, including through a new adjudication procedure for certain payment disputes between small businesses and larger businesses.
Importantly for construction practitioners, disputes already falling within the statutory adjudication regime for construction contracts will be excluded from that scheme.
The familiar Construction Act adjudication regime will therefore remain the principal statutory dispute resolution procedure for payment disputes arising under qualifying construction contracts.
What should the construction industry be doing now?
The Bill is still passing through Parliament, so wholesale amendment of contract suites would be premature.
However, businesses can start considering how their contractual arrangements may need to change. In particular:
Employers and developers should consider what security they will require in place of retentions and whether their standard forms adequately protect them in relation to defects and outstanding works.
Main contractors should review both upstream and downstream payment provisions. The proposals may affect not only what they receive from employers but also the mechanisms they operate across substantial subcontractor supply chains.
Contract administrators and project managers will need to understand the proposed seven-day restriction on pay less notices and ensure that payment processes leave sufficient time for payment applications to be assessed and notices to be prepared and served.
Contractors and subcontractors should review contractual provisions dealing with interest and retentions, particularly as the commencement and transitional provisions become clearer.
The Bill’s passage should also be monitored carefully. It is currently before the House of Commons and therefore remains subject to amendment before Royal Assent.
A shift in construction payment practice
The Commercial Payments Bill could mark the next major reform of construction payment practice.
Stronger payment rights, mandatory interest and the abolition of retentions could improve cashflow down the supply chain. Those procuring construction work will, however, need to rethink how they manage performance, defects and payment risks without cash retentions.
The detail will depend on the final legislation and accompanying regulations. Construction businesses should prepare to review their standard contracts, payment procedures and performance security before the new regime takes effect.
This article reflects the Commercial Payments Bill as brought from the House of Lords and introduced into the House of Commons on 21 October 2026. The legislation remains subject to amendment.
How we can help
If you would like advice or assistance with an adjudication, our dedicated construction team is here to help.
Talk to us about
Related services